Originally posted by: Luis



Hi All,

I have a customer that has two 9570V and they want to upgrade the whole system to something bigger. I was thinking of implementing a three Data Centers models but reutilizing one 9570V, like this:

Primary Site (< 1 km) Secondary Site (Near) (80 km) Third Site (Far)
NSC55 -------------------------> NSC55 ------------------------------------------------> 9570V
TC Synchronous / ShadowImage to a virtual LUN (Async)

Is it possible to do that??
what are the pro's and con's of this model??

I don't want to think about three NSC55 and Universal Replicator due to higher costs.

Thanks in advance.

Regards,
Luis